Building with Purpose: Silver Cliffs Q1 Update

·

May 5, 2026
Silver Cliffs saw steady progress in Q1 2026, with major infrastructure completed in early phases and continued advancement across grading, utilities, and roadway development.

Phase 1

  • Silver cliffs Drive utilities Sewer, Storm drain, Water, Gas, Power, and fiber installed from main street. Tested and complete.
  • Silver cliffs drive road prep and road base laid down.
  • Utility laterals in progress for each lot.

Phase 2

  • Silver Cliffs drive road base and Curb and gutter installed from Marys Crossing to reflective Street.
  • Utility’s installed and tested. Gas will be installed soon. All sleeves have been installed.
  • Curb and gutter installed. Road base installed and compacted.
  • 41 street light bases installed.
  • Utility laterals Installed.
  • Road base and curb and gutter installed 90%.
  • Rock wall installation.
  • Sewer lift station installed and tested.

Phase 4

  • Silver Cliffs drive road base and Curb and gutter installed from Marys Crossing to reflective Street.
  • Utility’s installed and tested. Gas will be installed soon. All sleeves have been installed.
  • Curb and gutter installed. Road base installed and compacted.
  • 41 street light bases installed.
  • Utility laterals Installed.
  • Road base and curb and gutter installed 90%.
  • Rock wall installation.
  • Sewer lift station installed and tested.

Phase 5

  • Sewer Lift station installation.

Phase 6

  • Iconic Parkway road prep.