Silver Cliffs saw steady progress in Q1 2026, with major infrastructure completed in early phases and continued advancement across grading, utilities, and roadway development.
Phase 1
- Silver cliffs Drive utilities Sewer, Storm drain, Water, Gas, Power, and fiber installed from main street. Tested and complete.
- Silver cliffs drive road prep and road base laid down.
- Utility laterals in progress for each lot.
Phase 2
- Silver Cliffs drive road base and Curb and gutter installed from Marys Crossing to reflective Street.
- Utility’s installed and tested. Gas will be installed soon. All sleeves have been installed.
- Curb and gutter installed. Road base installed and compacted.
- 41 street light bases installed.
- Utility laterals Installed.
- Road base and curb and gutter installed 90%.
- Rock wall installation.
- Sewer lift station installed and tested.
Phase 4
- Silver Cliffs drive road base and Curb and gutter installed from Marys Crossing to reflective Street.
- Utility’s installed and tested. Gas will be installed soon. All sleeves have been installed.
- Curb and gutter installed. Road base installed and compacted.
- 41 street light bases installed.
- Utility laterals Installed.
- Road base and curb and gutter installed 90%.
- Rock wall installation.
- Sewer lift station installed and tested.
Phase 5
- Sewer Lift station installation.
Phase 6
- Iconic Parkway road prep.
Progress Gallery